§ 1045.23. CAPACITY REQUIRED.  


Latest version.
  • Connection to a public sewer will not be allowed unless there is capacity available (in both wastewater volume and strength) at the POTW treatment plant and in all downstream sewers, pump stations, interceptors, and force mains, including, but not limited to, adequate capacity to accept, treat and dispose of BOD, TSS, or similar materials as required by applicable local, State or Federal laws, rules or regulations, as determined by the POTW.

(Ord. 446. Passed 1-23-12.)